BIM Based Time Management Among Construction Contractors in Turkey

An Interview Study

Authors

  • Ayşen Saraç Çıracıoğlu
    Affiliation
    Department of Architecture, Faculty of Architecture, Istanbul Technical University, 34367 Şişli, Istanbul, 2 Taşkışla Street, Turkey
  • Hakan Yaman
    Affiliation
    Department of Architecture, Faculty of Architecture, Istanbul Technical University, 34367 Şişli, Istanbul, 2 Taşkışla Street, Turkey
https://doi.org/10.3311/PPar.17918

Abstract

In both developing and industrialised countries, due to numerous time-related problems of construction projects, BIM-based time management, 4D BIM, plays an increasingly critical role within the industry. This study investigates the planning and scheduling problems, BIM application level, and BIM-based scheduling implementation by the lead construction companies in Turkey.
Despite the critical importance of the planning department in construction companies, the planning and BIM integration levels have scarcely been investigated from the contractor perspective in Turkey.
This paper presents the outcomes of 16 semi-structured interviews (SSI) with managers of the leading Turkish contractors selected from 100 of ENR’s 2019 Top 250 International Contractors list; a list of issues are outlined. The current situation escalates problems like tendering with missing project documents, examining 2D project drawings while scheduling, fragmentation, project manager’s reluctance to use and follow the project schedule, issues with updating the schedule as per construction improvements and quantities, and a lack of investment for BIM implementation. The research findings, ultimately, aim to help contractors improve their processes. Although this study’s findings are obtained from interviews with lead Turkish contractors, it is not limited in terms of geographic context since the interviewed contractors work worldwide.

Keywords:

BIM, 4D, time management, construction, Turkey

Citation data from Crossref and Scopus

Published Online

2021-12-21

How to Cite

Saraç Çıracıoğlu, A., Yaman, H. (2021) “BIM Based Time Management Among Construction Contractors in Turkey: An Interview Study”, Periodica Polytechnica Architecture, 52(2), pp. 192–204. https://doi.org/10.3311/PPar.17918

Issue

Section

Articles